MR-26-0094
Booked in T-C28080MLD-C280-80 — Isoflex coupling element moulding — 280 mm PCD, 80 Shore A · Gold Coast Urethane Systems
17 / 29
accepted against the run over 11 pours · 3 scrapped at the tool (85% yield)
12 to go
at 2 a day, about 6 more days — around 13 Aug 2026
Poured to the run, not to a quantity. Whatever comes off the tool that day gets booked in against it.
What came off the tool, day by day
This is the shape the mould shop actually delivers in.
Pours
11 booked in| Date | Poured | Accepted | Scrapped | Lot | Operator | Note |
|---|---|---|---|---|---|---|
| 21 July 2026 | 1 | 0 | 1 | — | D. Kovac | One short-filled, scrapped at the tool. |
| 20 July 2026 | 2 | 2 | — | — | W. Tulloch | — |
| 19 July 2026 | 1 | 1 | — | — | D. Kovac | — |
| 18 July 2026 | 1 | 1 | — | — | W. Tulloch | — |
| 17 July 2026 | 3 | 2 | 1 | — | W. Tulloch | One short-filled, scrapped at the tool. |
| 16 July 2026 | 1 | 0 | 1 | — | S. Rennick | One short-filled, scrapped at the tool. |
| 15 July 2026 | 3 | 3 | — | — | S. Rennick | — |
| 14 July 2026 | 3 | 3 | — | — | W. Tulloch | — |
| 13 July 2026 | 1 | 1 | — | — | S. Rennick | — |
| 12 July 2026 | 2 | 2 | — | — | S. Rennick | — |
| 11 July 2026 | 2 | 2 | — | — | W. Tulloch | — |
The run
- Moulding
- MLD-C280-80
- Mould shop
- Gold Coast Urethane Systems
- Tool
- T-C28080
- Ordered
- 29 pieces
- Rate
- 2 a day off this tool
- Durometer
- 80 Shore A
- Opened
- 09 July 2026 · 30 days ago
- Target
- 28 July 2026
- Closed
- 03 Aug 2026
- Raised by
- MT
Where these go
0 of MLD-C280-80 on the
shelf at Coomera. Each one is about a short job on
the CNC away from being a machined sub-assembly, and a few minutes after that from being a finished mount.