WO-26-0139
On the floor Machining60 × SA-V254-AST-75 — S Type adjusting stud sub-assembly — 254 mm, 75 Shore A
Short on 1 component
Planned
Materials ready
On the floor
QA & pack
Complete
What it consumes
What has to be on the shelf before this can run.
| Part number | Stage | Needed | Issued | On hand | Lot |
|---|---|---|---|---|---|
| MLD-V254-75 Isoflex co-polymer moulding — 254 mm body, 75 Shore A | Moulding | 60 | — | 38 22 short | PL-26-2186 |
This cannot run until the shortfall is covered. Availability will say whether those components can
themselves be made up out of what is on the shelf — a moulding machined into a sub-assembly, most often.
Open availability
Works order
- Makes
- 60 × SA-V254-AST-75
- Kind
- Machining
- Work centre
- CNC 1
- Time booked
- 30 min
- Per piece
- 30 s each
- Where
- Coomera Works
- Raised
- 04 Aug 2026
- Due
- 15 Aug 2026 · in 7 days
- Completed
- —
- Owner
- Tyson Blakely
- Value at list
- $22,305
Move it
The board drags too — this is here for touch.